James Garner Avenue Phase II

The James Garner Phase II extension creates a new uninterrupted corridor into Downtown Norman from Flood Avenue.  The project stretches from just north of Acres Street, adjacent to the new library, north over Robinson Street to connect with Flood Avenue. 

The project will consist of a new two-lane divided street section, a new bridge over Robinson Street, and a new roundabout intersection at Flood Avenue, along with realignment of portions of the Legacy Trail to provide a pedestrian and bicycle path as well.  

The project will provide an alternative route to downtown in an effort to relieve traffic congestion within nearby neighborhoods and on both Flood Avenue and Porter Avenue.

2019 Transportation Bond Project

Key Design Aspects

  • Looped Streets

  • Robinson Street Bridge

  • Roundabout at Flood Avenue

  • Right-of-Way and Utilities

  • Legacy Trail and Project Aesthetics


Projected Schedule

  • Finalize all R/W Acquisitions and Easements - Complete

  • Final Plans Specifications and Estimates - Complete

  • Open Bids - October 2022

  • Begin Construction - February 2023

  • Complete Construction - May 2024

 