The first is to modify the roadway configuration from the current one-way westbound configuration, to two-way traffic both east and westbound. This will require new roadway striping, reconfiguration of angled parking along the street, and new signalization equipment at intersections as well as the BNSF railroad crossing.

Secondly, the project will incorporate streetscape elements similar to those being implemented along Porter Avenue and Main Street.

 

Projected Schedule

Begin Utility Relocations (if needed) – August 2022

Final Plans, Specifications, and Estimates – July 2023

Open Bids – March 2024

Begin Construction – June 2024

Complete Construction – June 2025

 